Staging of Works

Stage 1:        Construction of new 7 bed wing and fully commissioned


Stage 2:        Relocate the 3 residents in the old house section of Home 3 to the new 7 bed wing and construct new

kitchen, staff room, bed 13 and new store.


Stage 3:        Relocate 4 residents from Home 3 to new 7 bed wing and renovate ensuites and bedrooms. Construct

staff base 3.


Stage 4:          Relocate next 4 residents in Home 3 to newly renovated rooms and renovate ensuites and bedrooms.


Stage 5:          Relocate final 4 residents in Home 3 to newly renovated rooms and renovate ensuites and bedrooms.


Stage 6:          Upon completion and commissioning of Stage 2 complete the remaining works: CACPS Office and

Store, Activities Co-ordinator and Hairdresser, Staff Bases 2&3, Door to middle wing living/dining room, linen alcove and

lifting machine cupboard, cleaners’ sink in dirty utility.

Stage 7:          Realignment of front driveway and new canopy to current service entry.